Country snapshot · West Africa

Burkina Faso

Export rules: PartialData as of 10 October 2026
32.2MW
Solar added in 2026 (Ember estimate, all segments)1N2,N3
−57%
Change on 20251
2025: 75.7 MW (Ember estimate)
34.0%
Access to electricity, 20242N4
15.54million
People without electricity, 2024 (DERCA calculation)2N4

Solar added each year

Ember estimates of all solar (utility-scale, distributed and off-grid), MW. 2026 is Ember’s full-year estimate.

Burkina Faso: solar added per year, 2023–2026, MW (Ember estimates)2023: 79.4 MW; 2024: 99.8 MW; 2025: 75.7 MW; 2026 estimate: 32.2 MW79.4202399.8202475.7202532.22026E
Burkina Faso: solar added per year, 2023–2026, MW (Ember estimates)2023: 79.4 MW; 2024: 99.8 MW; 2025: 75.7 MW; 2026 estimate: 32.2 MW79.4202399.8202475.7202532.22026E
View as tableHide table
Solar added per year, MW
YearMWBasis
202379.4Ember estimate
202499.8Ember estimate
202575.7Ember estimate
2026E32.2Ember estimate, full year

0.2% of Africa’s estimated 2026 solar additions (32.2 of 17,449.4 MW).1

Who has electricity

Share of people with access to electricity, 2024: rural and urban.

Burkina Faso: access to electricity, rural vs urban, 2024Rural 12.7%, urban 87.8%, national 34.0%.National 34.0%Rural 12.7%Urban 87.8%0%25%50%75%100%
Burkina Faso: access to electricity, rural vs urban, 2024Rural 12.7%, urban 87.8%, national 34.0%.National 34.0%Rural 12.7%Urban 87.8%0%50%100%
View as tableHide table
Access to electricity, 2024
AreaAccessYear
Rural12.7%2024
Urban87.8%2024
National34.0%2024
Rural 12.7%Urban 87.8%Without electricity 15.54m (DERCA calculation)

World Bank WDI, 2024.2

How reliable is the grid for business?

Firms experiencing electrical outages (2024 survey), compared with Sub-Saharan Africa and the world.3,4N5

Burkina Faso: share of firms experiencing electrical outagesBurkina Faso 92.5% (2024 survey); Sub-Saharan Africa 72.4%; World 47.5% (2025).Burkina Faso (2024)92.5%Sub-Saharan Africa72.4%World47.5%
Burkina Faso: share of firms experiencing electrical outagesBurkina Faso 92.5% (2024 survey); Sub-Saharan Africa 72.4%; World 47.5% (2025).Burkina Faso(2024)92.5%Sub-SaharanAfrica72.4%World47.5%

92.5% (2024 survey) · Sub-Saharan Africa 72.4% · World 47.5% (2025)

The rules for small-scale generationN1,N6

Export rules: Partial

Regulator
ARSE
Main utility
SONABEL
Export rulesDecree 2019-0902 covers self-producer grid access and buy-back; its tariff order has not been adopted. No net-metering tariff.5Medium confidenceShow detail

Décret n°2019-0902 covers autoproducer grid access and buy-back, and appears to be in force. Its tariff arrêté had **not** been adopted. Décret n°2020-1053 sets autoproduction conditions. No tariff structure applies directly to net metering.

Sources: 5
How exports are creditedSurplus paid by contract (six contracts reviewed paid 48 FCFA/kWh); sale capped at 30% of installed capacity.5Medium confidenceShow detail

The grid operator must pay for surplus it takes. Grid connection for sale is capped at 30% of installed capacity. No national tariff exists, so prices are set by contract; six contracts reviewed paid 48 FCFA/kWh.

Sources: 5
Size limits and licensingSelf-generation: declaration to 500 kW, authorisation above; renewables ≤5 kW exempt.5Medium confidenceShow detail

**Autoproduction:** declaration up to 500 kW; authorisation above 500 kW (Décret 2020-1053). RE systems of 5 kW or less are exempt from declaration. **Independent production:** declaration up to 250 kW; authorisation from 250 to 1,000 kW; licence above 1,000 kW.

Sources: 5
Mini-grid rulesNo dedicated regime described.5Medium confidenceShow detail

No dedicated mini-grid regime is described. Décret n°2020-0255 covers concessions and distribution authorisations.

Sources: 5
Market access beyond the utilityEligible clients (≥50 MW, 300,000 MWh/yr) may contract directly with a producer.5Medium confidenceShow detail

SONABEL holds the transmission monopoly, which covers third-party access to transmission. An "eligible client" (at least 50 MW and 300,000 MWh a year) may contract directly with a producer.

Sources: 5
Aggregation / VPP rulesNone foundShow detail

None found

“None found” means we could not locate a rule in public sources reviewed to 10 October 2026, not that one cannot exist.

Recent developments

Dated developments, 2024–2026.

  1. Jun 2026

    Mission 300 compact.6

  2. Aug 2025

    Regulator reported 161 MWc of solar installed in 2024.6

The full report

This is a snapshot. The full story is in Africa’s Invisible Grid.

The full analysis, with 17 exhibits on the boom, the data gap, the economics and the four building blocks, is in Africa’s Invisible Grid.

Get the full report

Africa’s Invisible Grid (PDF, 30 pages). Enter your details and we’ll email you a link to the report.