Country snapshot · East Africa
Eritrea
Solar added each year
Ember estimates of all solar (utility-scale, distributed and off-grid), MW. 2026 is Ember’s full-year estimate.
View as tableHide table
| Year | MW | Basis |
|---|---|---|
| 2023 | 0.6 | Ember estimate |
| 2024 | 0.1 | Ember estimate |
| 2025 | 37.4 | Ember estimate |
| 2026E | 1.0 | Ember estimate, full year |
0.0% of Africa’s estimated 2026 solar additions (1.0 of 17,449.4 MW).1
Who has electricity
Share of people with access to electricity, 2024: rural and urban.
View as tableHide table
| Area | Access | Year |
|---|---|---|
| Rural | 43.2% | 2024 |
| Urban | 78.1% | 2024 |
| National | 55.3% | 2024 |
World Bank WDI, 2024.2
How reliable is the grid for business?
Firms experiencing electrical outages (2009 survey), compared with Sub-Saharan Africa and the world.3,4N1,N7
20.5% (2009 survey) · Sub-Saharan Africa 72.4% · World 47.5% (2025)
The rules for small-scale generationN2,N8
Export rules: None found
- Regulator
- Electricity Regulatory Committee (not independent)
- Main utility
- Eritrean Electricity Corporation
Export rulesNone found. Feed-in tariffs are mentioned in policy but not implemented.5Medium confidenceShow detail
None found. FiTs are mentioned in policy but not implemented
How exports are creditedNone foundShow detail
None found
Size limits and licensingNone found5Low confidenceShow detail
None found. Model permits were drafted in 2007 and "need to be revised"
Mini-grid rulesNone. No regulations for isolated networks.5Medium confidenceShow detail
None. Regulations for isolated networks do not exist
Market access beyond the utilityPrivate actors foreseen in law (2004) but network access not implemented.5Medium confidenceShow detail
Proclamation 141/2004 foresees private actors, but network access is not implemented. The only IPP is Bisha mine (20 MW, oil)
Aggregation / VPP rulesNone foundShow detail
None found
“None found” means we could not locate a rule in public sources reviewed to 10 October 2026, not that one cannot exist.
Recent developments
Dated developments, 2024–2026.
The full report
This is a snapshot. The full story is in Africa’s Invisible Grid.
The full analysis, with 17 exhibits on the boom, the data gap, the economics and the four building blocks, is in Africa’s Invisible Grid.