Country snapshot · North Africa
Libya
Solar added each year
Ember estimates of all solar (utility-scale, distributed and off-grid), MW. 2026 is Ember’s full-year estimate.
View as tableHide table
| Year | MW | Basis |
|---|---|---|
| 2023 | 6.6 | Ember estimate |
| 2024 | 6.5 | Ember estimate |
| 2025 | 8.2 | Ember estimate |
| 2026E | 9.8 | Ember estimate, full year |
0.1% of Africa’s estimated 2026 solar additions (9.8 of 17,449.4 MW).1
Who has electricity
Share of people with access to electricity, 2024: rural and urban.
View as tableHide table
| Area | Access | Year |
|---|---|---|
| Rural | – | 2024 |
| Urban | 100.0% | 2024 |
| National | 77.4% | 2024 |
– Not available in sources reviewed. See the notes at the foot of the page.
World Bank WDI, 2024.2
How reliable is the grid for business?
Firms experiencing electrical outages, compared with Sub-Saharan Africa and the world.3,4N3,N8
No survey dataN3,N8 · Sub-Saharan Africa 72.4% · World 47.5% (2025)
The rules for small-scale generationN4,N9
Export rules: None found
- Regulator
- No dedicated electricity regulator; REAOL covers renewables
- Main utility
- GECOL (state utility)
Export rulesNone found. No comprehensive renewable-energy legal framework and no statutory feed-in tariff.5Medium confidenceShow detail
None found. No comprehensive RE legal framework and no statutory FiT
How exports are creditedNone found5Medium confidenceShow detail
None found. Pricing for RE projects is set by contract
Size limits and licensingNone foundShow detail
None found
Mini-grid rulesNone foundShow detail
None found
Market access beyond the utilityNone found. The offtaker is usually a public entity (GECOL).5Medium confidenceShow detail
None found. Offtaker is usually a public entity under Law 17/1984 (GECOL)
Aggregation / VPP rulesNone foundShow detail
None found
“None found” means we could not locate a rule in public sources reviewed to 10 October 2026, not that one cannot exist.
Recent developments
Dated developments, 2024–2026.
- Aug 2025
$10bn solar programme announced, targeting 4 GW by 2035 (headline only; low confidence).6
The full report
This is a snapshot. The full story is in Africa’s Invisible Grid.
The full analysis, with 17 exhibits on the boom, the data gap, the economics and the four building blocks, is in Africa’s Invisible Grid.