Country snapshot · East Africa

Madagascar

Export rules: PartialData as of 10 October 2026
116.8MW
Solar added in 2026 (Ember estimate, all segments)1N3,N4
+50%
Change on 20251
2025: 77.9 MW (Ember estimate)
42.5%
Access to electricity, 20242N5
18.38million
People without electricity, 2024 (DERCA calculation)2N5

Solar added each year

Ember estimates of all solar (utility-scale, distributed and off-grid), MW. 2026 is Ember’s full-year estimate.

Madagascar: solar added per year, 2023–2026, MW (Ember estimates)2023: 51.3 MW; 2024: 92.4 MW; 2025: 77.9 MW; 2026 estimate: 116.8 MW51.3202392.4202477.92025116.82026E
Madagascar: solar added per year, 2023–2026, MW (Ember estimates)2023: 51.3 MW; 2024: 92.4 MW; 2025: 77.9 MW; 2026 estimate: 116.8 MW51.3202392.4202477.92025116.82026E
View as tableHide table
Solar added per year, MW
YearMWBasis
202351.3Ember estimate
202492.4Ember estimate
202577.9Ember estimate
2026E116.8Ember estimate, full year

0.7% of Africa’s estimated 2026 solar additions (116.8 of 17,449.4 MW).1

Who has electricity

Share of people with access to electricity, 2024: rural and urban.

Madagascar: access to electricity, rural vs urban, 2024Rural 26.5%, urban 75.9%, national 42.5%.National 42.5%Rural 26.5%Urban 75.9%0%25%50%75%100%
Madagascar: access to electricity, rural vs urban, 2024Rural 26.5%, urban 75.9%, national 42.5%.National 42.5%Rural 26.5%Urban 75.9%0%50%100%
View as tableHide table
Access to electricity, 2024
AreaAccessYear
Rural26.5%2024
Urban75.9%2024
National42.5%2024
Rural 26.5%Urban 75.9%Without electricity 18.38m (DERCA calculation)

World Bank WDI, 2024.2

How reliable is the grid for business?

Firms experiencing electrical outages (2022 survey), compared with Sub-Saharan Africa and the world.3,4N6

Madagascar: share of firms experiencing electrical outagesMadagascar 52.4% (2022 survey); Sub-Saharan Africa 72.4%; World 47.5% (2025).Madagascar (2022)52.4%Sub-Saharan Africa72.4%World47.5%
Madagascar: share of firms experiencing electrical outagesMadagascar 52.4% (2022 survey); Sub-Saharan Africa 72.4%; World 47.5% (2025).Madagascar (2022)52.4%Sub-SaharanAfrica72.4%World47.5%

52.4% (2022 survey) · Sub-Saharan Africa 72.4% · World 47.5% (2025)

The rules for small-scale generationN2,N7

Export rules: Partial

Regulator
ARELEC
Main utility
JIRAMA
CrossBoundary Energy regulatory stage5N1,N8
Stage 1
Stage 0
Centralised control
Stage 1
Cautious co-existence
Stage 2
Directed benefits
Stage 3
Early market management
Export rulesNo net-metering scheme. Electricity Code 2017 lets renewable self-producers sell up to 40% of annual output, on ARELEC conditions (not found).6Medium confidenceShow detail

No net-metering scheme found. The Code allows renewable autoproducers to sell surplus to the grid (Art. 14/46), with ≥60% for own use, so sales are ≤40% of annual production, under conditions set by ARELEC. Implementing conditions were not found.

Sources: 6
How exports are creditedNone found; terms set by ARELEC.Show detail

None found. Terms are set by ARELEC and were not located.

Size limits and licensingDeclaration up to 500 kW (solar, hydro, thermal) or 1 MW (wind, biomass, geothermal); authorisation above.6Low confidenceShow detail

Autoproduction under the declaration regime: ≤500 kW for thermal/hydro/solar and ≤1 MW for biomass/geothermal/wind/waste (Art. 42). Authorisation applies above that. Art. 28 values (solar PV ≤150 kW) are corrupted in the source.

Sources: 6
Mini-grid rulesNo dedicated regulation; the Code defines isolated centres and ADER leads rural electrification.6High confidenceShow detail

No dedicated mini-grid regulation found. The Code defines "Centre Isolé" (mini-réseau), and ADER leads rural electrification (Title VIII).

Sources: 6
Market access beyond the utilityNetwork operators must interconnect new operators on request; ARELEC may authorise direct supply contracts.6High confidenceShow detail

Art. 26: obligation to interconnect new operators. Art. 27: ARELEC may authorise direct supply contracts. Art. 48: private lines on private property are free.

Sources: 6
Aggregation / VPP rulesNone foundShow detail

None found

“None found” means we could not locate a rule in public sources reviewed to 10 October 2026, not that one cannot exist.

Recent developments

Dated developments, 2024–2026.

  1. May 2026

    World Bank approved US$250m for JIRAMA reform and solar hybridisation of 30 isolated plants.7,8

  2. Nov 2025

    Rotating load-shedding on the Antananarivo grid.7,8

The full report

This is a snapshot. The full story is in Africa’s Invisible Grid.

The full analysis, with 17 exhibits on the boom, the data gap, the economics and the four building blocks, is in Africa’s Invisible Grid.

Get the full report

Africa’s Invisible Grid (PDF, 30 pages). Enter your details and we’ll email you a link to the report.