Country snapshot · West Africa

Niger

Export rules: PartialData as of 10 October 2026
37.5MW
Solar added in 2026 (Ember estimate, all segments)1N1,N2
+38%
Change on 20251
2025: 27.1 MW (Ember estimate)
21.3%
Access to electricity, 20242N3
21.27million
People without electricity, 2024 (DERCA calculation)2N3

Solar added each year

Ember estimates of all solar (utility-scale, distributed and off-grid), MW. 2026 is Ember’s full-year estimate.

Niger: solar added per year, 2023–2026, MW (Ember estimates)2023: 10.3 MW; 2024: 18.9 MW; 2025: 27.1 MW; 2026 estimate: 37.5 MW10.3202318.9202427.1202537.52026E
Niger: solar added per year, 2023–2026, MW (Ember estimates)2023: 10.3 MW; 2024: 18.9 MW; 2025: 27.1 MW; 2026 estimate: 37.5 MW10.3202318.9202427.1202537.52026E
View as tableHide table
Solar added per year, MW
YearMWBasis
202310.3Ember estimate
202418.9Ember estimate
202527.1Ember estimate
2026E37.5Ember estimate, full year

0.2% of Africa’s estimated 2026 solar additions (37.5 of 17,449.4 MW).1

Who has electricity

Share of people with access to electricity, 2024: rural and urban.

Niger: access to electricity, rural vs urban, 2024Rural 10.8%, urban 69.1%, national 21.3%.National 21.3%Rural 10.8%Urban 69.1%0%25%50%75%100%
Niger: access to electricity, rural vs urban, 2024Rural 10.8%, urban 69.1%, national 21.3%.National 21.3%Rural 10.8%Urban 69.1%0%50%100%
View as tableHide table
Access to electricity, 2024
AreaAccessYear
Rural10.8%2024
Urban69.1%2024
National21.3%2024
Rural 10.8%Urban 69.1%Without electricity 21.27m (DERCA calculation)

World Bank WDI, 2024.2

How reliable is the grid for business?

Firms experiencing electrical outages (2025 survey), compared with Sub-Saharan Africa and the world.3,4N4

Niger: share of firms experiencing electrical outagesNiger 75.1% (2025 survey); Sub-Saharan Africa 72.4%; World 47.5% (2025).Niger (2025)75.1%Sub-Saharan Africa72.4%World47.5%
Niger: share of firms experiencing electrical outagesNiger 75.1% (2025 survey); Sub-Saharan Africa 72.4%; World 47.5% (2025).Niger (2025)75.1%Sub-SaharanAfrica72.4%World47.5%

75.1% (2025 survey) · Sub-Saharan Africa 72.4% · World 47.5% (2025)

The rules for small-scale generationN5

Export rules: Partial

Regulator
ARSE
Main utility
NIGELEC
Export rulesElectricity Code 2016 lets self-producers sell surplus with ministerial authorisation; implementing decree not found.5,6High confidenceShow detail

No net-metering or feed-in framework found. Code 2016, Art. 45 lets an autoproducer sell surplus to a licensed delegate with ministerial authorisation. Art. 47 refers the conditions to a decree, which was not found. Art. 46 bars grid connection without express ministerial authorisation.

Sources: 5, 6
How exports are creditedNone found5,6High confidenceShow detail

None found. No price for autoproducer surplus. Art. 64 is a general rule: tariffs negotiated between operators, subject to regulator approval.

Sources: 5, 6
Size limits and licensingDeclaration below 20 kW; ministerial authorisation above.5,6High confidenceShow detail

Declaration below 20 kW; prior ministerial authorisation above 20 kW, after the regulator's opinion.

Sources: 5, 6
Mini-grid rulesMini-grid law drafted; status unclear.5,6Medium confidenceShow detail

AEP says a mini-grid law "a été élaborée" (has been drafted), but its recommendations say it still needs to be passed, so its status is unclear. The Code has no mini-grid chapter; rural electrification falls under Art. 44.

Sources: 5, 6
Market access beyond the utilityThird-party access in the Code; direct sales to consumers above 10 MW.5,6High confidenceShow detail

Third-party access is in the Code: the regulator ensures fair access (Art. 8), transport operators cannot refuse (Art. 29), and a toll applies (Art. 30). Producers may sell directly to large consumers above 10,000 kW (Art. 24). AEP says there is no distribution grid code yet.

Sources: 5, 6
Aggregation / VPP rulesNone foundShow detail

None found

“None found” means we could not locate a rule in public sources reviewed to 10 October 2026, not that one cannot exist.

Recent developments

Dated developments, 2024–2026.

  1. Apr 2025

    Load-shedding continues; imports from Nigeria reduced; rooftop solar booming (minister).7

  2. Jan 2025

    Mission 300 compact.7

The full report

This is a snapshot. The full story is in Africa’s Invisible Grid.

The full analysis, with 17 exhibits on the boom, the data gap, the economics and the four building blocks, is in Africa’s Invisible Grid.