Country snapshot · West Africa

Senegal

Export rules: PartialData as of 10 October 2026
343.7MW
Solar added in 2026 (Ember estimate, all segments)1N2,N3
−9%
Change on 20251
2025: 378.3 MW (Ember estimate)
82.9%
Access to electricity, 20242N4
3.16million
People without electricity, 2024 (DERCA calculation)2N4

Solar added each year

Ember estimates of all solar (utility-scale, distributed and off-grid), MW. 2026 is Ember’s full-year estimate.

Senegal: solar added per year, 2023–2026, MW (Ember estimates)2023: 135.3 MW; 2024: 367.6 MW; 2025: 378.3 MW; 2026 estimate: 343.7 MW135.32023367.62024378.32025343.72026E
Senegal: solar added per year, 2023–2026, MW (Ember estimates)2023: 135.3 MW; 2024: 367.6 MW; 2025: 378.3 MW; 2026 estimate: 343.7 MW135.32023367.62024378.32025343.72026E
View as tableHide table
Solar added per year, MW
YearMWBasis
2023135.3Ember estimate
2024367.6Ember estimate
2025378.3Ember estimate
2026E343.7Ember estimate, full year

2.0% of Africa’s estimated 2026 solar additions (343.7 of 17,449.4 MW).1

Who has electricity

Share of people with access to electricity, 2024: rural and urban.

Senegal: access to electricity, rural vs urban, 2024Rural 67.1%, urban 95.7%, national 82.9%.National 82.9%Rural 67.1%Urban 95.7%0%25%50%75%100%
Senegal: access to electricity, rural vs urban, 2024Rural 67.1%, urban 95.7%, national 82.9%.National 82.9%Rural 67.1%Urban 95.7%0%50%100%
View as tableHide table
Access to electricity, 2024
AreaAccessYear
Rural67.1%2024
Urban95.7%2024
National82.9%2024
Rural 67.1%Urban 95.7%Without electricity 3.16m (DERCA calculation)

World Bank WDI, 2024.2

How reliable is the grid for business?

Firms experiencing electrical outages (2024 survey), compared with Sub-Saharan Africa and the world.3,4N5

Senegal: share of firms experiencing electrical outagesSenegal 55.0% (2024 survey); Sub-Saharan Africa 72.4%; World 47.5% (2025).Senegal (2024)55.0%Sub-Saharan Africa72.4%World47.5%
Senegal: share of firms experiencing electrical outagesSenegal 55.0% (2024 survey); Sub-Saharan Africa 72.4%; World 47.5% (2025).Senegal (2024)55.0%Sub-SaharanAfrica72.4%World47.5%

55.0% (2024 survey) · Sub-Saharan Africa 72.4% · World 47.5% (2025)

The rules for small-scale generationN6

Export rules: Partial

Regulator
CRSE
Main utility
Senelec
CrossBoundary Energy regulatory stage5N1,N7
Stage 0
Stage 0
Centralised control
Stage 1
Cautious co-existence
Stage 2
Directed benefits
Stage 3
Early market management
Export rulesDecree 2023-286 on self-production (Feb 2023) covers surplus sale and grid injection; the surplus tariff mechanism is still to be set (Mission 300 compact).6,7High confidenceShow detail

Décret n° 2023-286 du 7 février 2023 relatif à l'activité d'autoproduction — covers surplus sale and grid injection. Status: in force (adopted 7 Feb 2023)

Sources: 6, 7
How exports are creditedDecree provides for surplus sale under contract at a CRSE-set tariff, but the tariff mechanism was still pending (Jan 2025 compact). Sold surplus capped at 10% of annual consumption (law-firm summary).6,7Medium confidenceShow detail

Surplus sold under purchase contract with the concessionnaire at a tariff set by CRSE; sold surplus capped at 10% of annual consumption (MAGP); M300 compact says a tariff-setting mechanism for surplus is still to be added

Sources: 6, 7
Size limits and licensingDeclaration up to 1 MW for solar PV; licence above. Sizing up to 120% of peak (domestic).6,7Medium confidenceShow detail

Declaration regime up to: solar PV 1 MW; thermal/hydro/wind 500 kW; biomass 2 MW; licence above; sales licence required whenever surplus is sold. Installed capacity ≤120% peak (domestic), ≤110% (professional)

Sources: 6, 7
Mini-grid rulesRural electrification concessions under the Electricity Code 2021.6,7Medium confidenceShow detail

Rural decentralised electrification concessions (CER) under Electricity Code (Law 2021-31); compact commits to "clearly defined" approval process for private mini-grids (target Aug 2025)

Sources: 6, 7
Market access beyond the utilityElectricity Code 2021: third-party network access and IPP sales to eligible customers.6,7High confidenceShow detail

Electricity Code Law 2021-31 (9 Jul 2021): third-party access to transmission/distribution; IPP sale to eligible customers; distribution concessions

Sources: 6, 7
Aggregation / VPP rulesNone foundShow detail

None found

“None found” means we could not locate a rule in public sources reviewed to 10 October 2026, not that one cannot exist.

Recent developments

Dated developments, 2024–2026.

  1. Jan 2025

    Mission 300 compact: universal access from 2029.6,7

The full report

This is a snapshot. The full story is in Africa’s Invisible Grid.

The full analysis, with 17 exhibits on the boom, the data gap, the economics and the four building blocks, is in Africa’s Invisible Grid.

Get the full report

Africa’s Invisible Grid (PDF, 30 pages). Enter your details and we’ll email you a link to the report.